Route 850 Bridge over Bixler Run Open to Traffic

Construction to be complete after Overlay Surface is applied to Bridge Deck Harrisburg, PA – A Route 850 (Fort Robinson Road) bridge spanning Bixler Run in Nort...
JV-290_P3 (002)

Construction to be complete after Overlay Surface is applied to Bridge Deck

Harrisburg, PA – A Route 850 (Fort Robinson Road) bridge spanning Bixler Run in Northeast Madison Township, Perry County, reopened to traffic today. This bridge was replaced as part of the Pennsylvania Department of Transportation’s (PennDOT) Rapid Bridge Replacement Project and allows PennDOT to remove it from the state’s structurally deficient bridge list.

With the bridge reopened, motorists may notice a slight bump as they drive across the bridge until a polyester polymer concrete (PPC) overlay is applied to the deck. This is often the final step in completing box beam bridge projects. The PPC overlay is designed to protect the deck from the wear and tear brought about by Pennsylvania’s harsh winters and reduce the long-term maintenance costs.

The polyester material can only be applied when temperatures are consistently above 40 degrees, dry weather is forecasted and after the bridge concrete has cured for at least 30 days. An alternating traffic pattern will be controlled by flaggers when the PPC overlay is applied in October 2017.

To find out when the overlay will be applied to this structure, visit http://www.parapidbridges.com/polyesterpolymerconcreteoverlay.html. In the event of unfavorable weather, this schedule may change. Any such changes will be posted on the website.

This bridge is referred to as JV-290 and is one out of the 558 bridges being replaced under the Rapid Bridge Replacement Project. JV references the joint-venture partnership between Walsh/Granite, which is leading construction for the entire project. Replacement work for this bridge was performed by Amelie Construction & Supply of Pittsburgh, PA.
The Rapid Bridge Replacement Project is a public-private partnership (P3) between PennDOT and Plenary Walsh Keystone Partners (PWKP), under which PWKP will finance, design, replace, and maintain the bridges for 25 years. The P3 approach will allow PennDOT to replace the bridges more quickly while achieving significant savings and minimizing impact on motorists.
To see the bridges included in the statewide initiative and to learn more about the Rapid Bridge Replacement Project, go to http://www.parapidbridges.com. To learn more about P3 in Pennsylvania, visit http://www.p3forpa.pa.gov.

Source: PennDOT